In the instance of this project recently completed for a confidential client, we provided VDC and fabrication of 5” conduit and custom bends to complete the section featured above, partnering with @NOX_Innovations. We mitigated all safety risks by utilizing a forklift to lift and install 12,000 linear ft of the 5” prefabricated conduit to a structured steel platform that would diminish the hazards of assembling the conduit in an elevated, open-air environment. While eliminating material handling hazards, this technique allowed up to 96” radius 90-degree bends to be installed.
By pulling approximately 37,000 linear ft of 750 kcmil cable at 35ft-45ft ft in the air, we provided power from new @srpconnect equipment to an electrical room of this manufacturing facility that requires extensive operational hours. In addition, our team accomplished an installation of four medium voltage switchgear lineups.